Mar 17, 2022Lille Square LondonUpdated: Mar 29, 2022Client: Keltbray structuresContract Period: 36 weeksValue: £750,000Scope of Works: The scope of works is we dealt with placing concrete on Substructure and Superstructures (Raft slab, Gf slab and verts) to 7th floor at C and D Blocks.
Client: Keltbray structuresContract Period: 36 weeksValue: £750,000Scope of Works: The scope of works is we dealt with placing concrete on Substructure and Superstructures (Raft slab, Gf slab and verts) to 7th floor at C and D Blocks.